Herder Drive Rehabilitation
This long-term project investigates and corrects the root causes of the roadway issues along Herder Drive and in Hewlett Park. The issues included:
- Pot holes
- Road heaves
- Higher than normal water levels
The investigation revealed the problems that were causing the poor conditions on Herder Drive:
At the Erickson Drive storm water crossing: This drainage route was too small and created a bottle neck
Along the drainage channels from Erickson Drive to Hewlett Park: The drainage channel was too flat. Water was standing instead of draining away
At the storm water mains within the roadways of Hewlett Park: The mains were too shallow and were too small to allow enough drainage
With groundwater conditions in the area: Because of 1 - 3, the water had nowhere to drain
How?
First, we corrected the problems causing poor conditions (1 - 3 above)
Next we repaired Hunter Road and Hinshaw Drive
Work continues to repair Herder Drive and then Harrison Road
Many projects were coordinated at the same time to maximize efficiency
What?
We improved surface and ground water drainage so that water moves from west to east, away from Hewlett Park. Improvements include:
Added the Hampton Pointe storm water lift station and new Hampton Pointe outfall
New Hampton Pointe storm water lift stationRegrading of drainage ditches and storm ponds
Added two large concrete box culverts at the Erickson Drive storm water crossing. The new culverts eliminate the bottleneck at the Erickson Drive storm water crossing. The old culverts were about 60 cm in diameter. The new box culverts are 1.6 meters tall and 2.9 meters wide
New Hampton Pointe Outfall (left),
New Erickson Drive storm water crossing box culvert (right)
Improved roadways:
- Stronger road structure
- Safer roadway for driving
Improved sightlines for pedestrians to cross roadway safely
Removal, replacement and upgrading the existing storm water mains
Installation of weeping tile drains along the roadway
Removal of concrete in areas where the ground settled, and the surface water is not draining properly
Removal and replacement of the asphalt roadway
Addition of traffic calming measures
Where?
Herder Drive rehabilitation takes place in phases, from:
Hinshaw Drive to Hagerman Road
Hagerman Road to Harrison Road
Harrison Road to 47 Avenue
When?
- Herder Drive rehabilitation takes place in phases
- View project phases and estimated timeline
Next Steps
Rehabilitation of Herder Drive from Hagerman Road to Harrison Road
Rehabilitation of Herder Drive from Harrison Road to 47 Avenue
Learn about the project
This long-term project investigates and corrects the root causes of the roadway issues along Herder Drive and in Hewlett Park. The issues included:
- Pot holes
- Road heaves
- Higher than normal water levels
The investigation revealed the problems that were causing the poor conditions on Herder Drive:
At the Erickson Drive storm water crossing: This drainage route was too small and created a bottle neck
Along the drainage channels from Erickson Drive to Hewlett Park: The drainage channel was too flat. Water was standing instead of draining away
At the storm water mains within the roadways of Hewlett Park: The mains were too shallow and were too small to allow enough drainage
With groundwater conditions in the area: Because of 1 - 3, the water had nowhere to drain
How?
First, we corrected the problems causing poor conditions (1 - 3 above)
Next we repaired Hunter Road and Hinshaw Drive
Work continues to repair Herder Drive and then Harrison Road
Many projects were coordinated at the same time to maximize efficiency
What?
We improved surface and ground water drainage so that water moves from west to east, away from Hewlett Park. Improvements include:
Added the Hampton Pointe storm water lift station and new Hampton Pointe outfall
New Hampton Pointe storm water lift stationRegrading of drainage ditches and storm ponds
Added two large concrete box culverts at the Erickson Drive storm water crossing. The new culverts eliminate the bottleneck at the Erickson Drive storm water crossing. The old culverts were about 60 cm in diameter. The new box culverts are 1.6 meters tall and 2.9 meters wide
New Hampton Pointe Outfall (left),
New Erickson Drive storm water crossing box culvert (right)
Improved roadways:
- Stronger road structure
- Safer roadway for driving
Improved sightlines for pedestrians to cross roadway safely
Removal, replacement and upgrading the existing storm water mains
Installation of weeping tile drains along the roadway
Removal of concrete in areas where the ground settled, and the surface water is not draining properly
Removal and replacement of the asphalt roadway
Addition of traffic calming measures
Where?
Herder Drive rehabilitation takes place in phases, from:
Hinshaw Drive to Hagerman Road
Hagerman Road to Harrison Road
Harrison Road to 47 Avenue
When?
- Herder Drive rehabilitation takes place in phases
- View project phases and estimated timeline
Next Steps
Rehabilitation of Herder Drive from Hagerman Road to Harrison Road
Rehabilitation of Herder Drive from Harrison Road to 47 Avenue
Learn about the project
-
August 4, 2026 Update
Share August 4, 2026 Update on Facebook Share August 4, 2026 Update on X (formerly Twitter) Share August 4, 2026 Update on Linkedin Email August 4, 2026 Update link
The final lift of asphalt is complete on Herder Drive between Harrison Road and 47 Avenue. The roadway is now open to the public.
During the week of August 3, crews will continue completing a few remaining finishing touches, including:
Line painting
Landscaping
Signage installation
Minor asphalt patching at corners
This work marks another milestone in the Town's long-term Herder Drive Rehabilitation project. This project corrects root causes of roadway issues along Herder Drive, such as potholes, road heaves, and higher than normal water levels. The project has been completed in phases to minimize impacts, while delivering lasting improvements to the area.
The final lift of asphalt is complete on Herder Drive between Harrison Road and 47 Avenue. The roadway is now open to the public.
During the week of August 3, crews will continue completing a few remaining finishing touches, including:
Line painting
Landscaping
Signage installation
Minor asphalt patching at corners
This work marks another milestone in the Town's long-term Herder Drive Rehabilitation project. This project corrects root causes of roadway issues along Herder Drive, such as potholes, road heaves, and higher than normal water levels. The project has been completed in phases to minimize impacts, while delivering lasting improvements to the area.
-
June 24, 2026 Update:
Share June 24, 2026 Update: on Facebook Share June 24, 2026 Update: on X (formerly Twitter) Share June 24, 2026 Update: on Linkedin Email June 24, 2026 Update: linkConstruction is underway for Herder Drive from Harrison Road to Herder Drive Trail (north of Heenan Crescent):
June 15 – July 10, 2026
- Concrete repairs
- Curbs
- Sidewalks
- Laying final layer of asphalt
- Line painting
- Landscaping
Construction is underway for Herder Drive from 47 Avenue to Harrison road:
June 22 - July 22:
- Replacing concrete curbs and sidewalks
- Removal of existing asphalt
- Roadway work
- Reshaping of gravel base
- There’ll be intermitted roadway closures and traffic disruptions during construction. At all times, we’ll ensure that people will have pedestrian access to their property. There’ll be times when parking along Herder Dr will not be allowed, and vehicular access to properties will not be allowed. We’ll be informing people in advance of any traffic disruptions. Find traffic interruptions and road closure announcements on the News Hub.
- Residents impacted by this work will receive advance notice
July 20 - July 31
- First and second final layer of asphalt
- There’ll be intermitted roadway closures and traffic disruptions during construction. At all times, we’ll ensure that people will have pedestrian access to their property. There’ll be times when parking along Herder Dr will not be allowed, and vehicular access to properties will not be allowed. We’ll be informing people in advance of any traffic disruptions. Find traffic interruptions and road closure announcements on the News Hub.
- Residents impacted by this work will receive advance notice
August 3 - August 8
- Landscaping
- Line Painting
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we must delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
Construction is underway for Herder Drive from Harrison Road to Herder Drive Trail (north of Heenan Crescent):
June 15 – July 10, 2026
- Concrete repairs
- Curbs
- Sidewalks
- Laying final layer of asphalt
- Line painting
- Landscaping
Construction is underway for Herder Drive from 47 Avenue to Harrison road:
June 22 - July 22:
- Replacing concrete curbs and sidewalks
- Removal of existing asphalt
- Roadway work
- Reshaping of gravel base
- There’ll be intermitted roadway closures and traffic disruptions during construction. At all times, we’ll ensure that people will have pedestrian access to their property. There’ll be times when parking along Herder Dr will not be allowed, and vehicular access to properties will not be allowed. We’ll be informing people in advance of any traffic disruptions. Find traffic interruptions and road closure announcements on the News Hub.
- Residents impacted by this work will receive advance notice
July 20 - July 31
- First and second final layer of asphalt
- There’ll be intermitted roadway closures and traffic disruptions during construction. At all times, we’ll ensure that people will have pedestrian access to their property. There’ll be times when parking along Herder Dr will not be allowed, and vehicular access to properties will not be allowed. We’ll be informing people in advance of any traffic disruptions. Find traffic interruptions and road closure announcements on the News Hub.
- Residents impacted by this work will receive advance notice
August 3 - August 8
- Landscaping
- Line Painting
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we must delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
- Concrete repairs
-
May 31, 2025 Update
Share May 31, 2025 Update on Facebook Share May 31, 2025 Update on X (formerly Twitter) Share May 31, 2025 Update on Linkedin Email May 31, 2025 Update link2025 construction is underway:
- Stormwater, roadway surface, and sidewalks
- Work on stormwater lines must happen after spring breakup
-
Underway: July - August 2025
- Herder Drive rehabilitation from Hewlett Park trail to south of Harrison Road
- Harrison Road rehabilitation from Herder Drive to Hallgren Drive
- July 8 update: Starting to remove asphalt and construction to follow shortly afterwards
-
Complete: May - June 2025
- Herder Drive from Hagerman Road to the Hewlett Park trail
- Concrete repairs and final layer of asphalt
2025 construction is underway:
- Stormwater, roadway surface, and sidewalks
- Work on stormwater lines must happen after spring breakup
-
Underway: July - August 2025
- Herder Drive rehabilitation from Hewlett Park trail to south of Harrison Road
- Harrison Road rehabilitation from Herder Drive to Hallgren Drive
- July 8 update: Starting to remove asphalt and construction to follow shortly afterwards
-
Complete: May - June 2025
- Herder Drive from Hagerman Road to the Hewlett Park trail
- Concrete repairs and final layer of asphalt
-
March 1, 2024 Update
Share March 1, 2024 Update on Facebook Share March 1, 2024 Update on X (formerly Twitter) Share March 1, 2024 Update on Linkedin Email March 1, 2024 Update linkProgress is underway on planning for 2024 construction:
-
2024 work includes Herder Drive rehabilitation from Hagerman Rd to approximately Heenan Cresent
- Stormwater, roadway surface, and sidewalks
- On February 14, 2024, we issued a tender for the roadway construction
- We hope to present our choice of construction contractor for Council approval on March 25
- We hope to begin construction in June, depending on weather
- Work on stormwater lines must happen after spring breakup
Progress is underway on planning for 2024 construction:
-
2024 work includes Herder Drive rehabilitation from Hagerman Rd to approximately Heenan Cresent
- Stormwater, roadway surface, and sidewalks
- On February 14, 2024, we issued a tender for the roadway construction
- We hope to present our choice of construction contractor for Council approval on March 25
- We hope to begin construction in June, depending on weather
- Work on stormwater lines must happen after spring breakup
-
2024 work includes Herder Drive rehabilitation from Hagerman Rd to approximately Heenan Cresent
-
August 16, 2023 Update
Share August 16, 2023 Update on Facebook Share August 16, 2023 Update on X (formerly Twitter) Share August 16, 2023 Update on Linkedin Email August 16, 2023 Update linkProgress on the Herder Drive rehabilitation is on schedule and on budget. This long-term project began in 2016 to investigate and correct the root causes of the roadway issues along Herder Drive and in Hewlett Park. The issues included potholes, road heaves, and higher than normal water levels.
Next Tasks
August 17 – 25: Road line painting on Herder Drive from Hinshaw Drive to Hagerman Road
Completed Tasks: August 4
Road Surface Infrastructure
We completed milling and paving on Herder Drive from Hinshaw Drive to Hagerman Road, including the intersection at Hinshaw Drive and Herder DriveContinue reading
Progress on the Herder Drive rehabilitation is on schedule and on budget. This long-term project began in 2016 to investigate and correct the root causes of the roadway issues along Herder Drive and in Hewlett Park. The issues included potholes, road heaves, and higher than normal water levels.
Next Tasks
August 17 – 25: Road line painting on Herder Drive from Hinshaw Drive to Hagerman Road
Completed Tasks: August 4
Road Surface Infrastructure
We completed milling and paving on Herder Drive from Hinshaw Drive to Hagerman Road, including the intersection at Hinshaw Drive and Herder Drive
-
Milling and paving starting today
Share Milling and paving starting today on Facebook Share Milling and paving starting today on X (formerly Twitter) Share Milling and paving starting today on Linkedin Email Milling and paving starting today linkWe are ready to begin milling and paving:
- Herder Drive: Hinshaw Drive to Hagerman Road, including the intersection at Hinshaw Drive and Herder Drive
- Hours: 7:30 AM to 4:00 PM
- One-way alternating traffic
- We are working hard to complete milling and paving before the August long weekend, weather permitting
- Thank you for watching out for our construction staff
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
We are ready to begin milling and paving:
- Herder Drive: Hinshaw Drive to Hagerman Road, including the intersection at Hinshaw Drive and Herder Drive
- Hours: 7:30 AM to 4:00 PM
- One-way alternating traffic
- We are working hard to complete milling and paving before the August long weekend, weather permitting
- Thank you for watching out for our construction staff
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
-
June 29, 2023 progress update
Share June 29, 2023 progress update on Facebook Share June 29, 2023 progress update on X (formerly Twitter) Share June 29, 2023 progress update on Linkedin Email June 29, 2023 progress update linkSo far, we have completed:
- Concrete sidewalks including new sidewalks and repairs to existing sidewalks
Asphalt work begins July 4:
- Mill and pave asphalt on Herder Drive, from Hinshaw Drive to Hagerman Road
Thanks for your patience and for watching out for our for construction crews!
So far, we have completed:
- Concrete sidewalks including new sidewalks and repairs to existing sidewalks
Asphalt work begins July 4:
- Mill and pave asphalt on Herder Drive, from Hinshaw Drive to Hagerman Road
Thanks for your patience and for watching out for our for construction crews!
-
Budget
Share Budget on Facebook Share Budget on X (formerly Twitter) Share Budget on Linkedin Email Budget link
The Herder Drive rehabilitation is one of the Town's biggest projects. It could not be completed in one construction season and was split into many phases. Budget information included is for recent phases only.
Total budget for 2023 - 2025: $2,192,812
2025
- Budget: $2,000,000 (Estimated)
- Funding Source: Reserves, capital funding, and grants
- Progress: Planning / scheduled
2024
- Budget: $100,000 (Estimated)
- Funding Source: Reserves
- Progress: Planning / scheduled
2023
- Budget: $92,812
- Funding Source: Reserves
- Progress: Underway
Questions?
The Herder Drive rehabilitation is one of the Town's biggest projects. It could not be completed in one construction season and was split into many phases. Budget information included is for recent phases only.
Total budget for 2023 - 2025: $2,192,812
2025
- Budget: $2,000,000 (Estimated)
- Funding Source: Reserves, capital funding, and grants
- Progress: Planning / scheduled
2024
- Budget: $100,000 (Estimated)
- Funding Source: Reserves
- Progress: Planning / scheduled
2023
- Budget: $92,812
- Funding Source: Reserves
- Progress: Underway
Questions?
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends
No thanks
-
June 22 → August 07 2026
-
June 15 → July 10 2026
-
March 01 → November 26 2025
-
May 15 → November 29 2024
-
April 20 → November 15 2023