Milling and paving starting today

We are ready to begin milling and paving:

  • Herder Drive: Hinshaw Drive to Hagerman Road, including the intersection at Hinshaw Drive and Herder Drive
  • Hours: 7:30 AM to 4:00 PM
  • One-way alternating traffic
  • We are working hard to complete milling and paving before the August long weekend, weather permitting
  • Thank you for watching out for our construction staff


Why can't we do construction projects according to a set schedule?

  • Weather is the boss of construction. If we have bad weather, we have to delay projects
  • Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
  • Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
  • There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time

We thank you for all your patience during construction to keep our workers safe!