May 31, 2025 Update

2025 construction is underway:

  • Stormwater, roadway surface, and sidewalks
  • Work on stormwater lines must happen after spring breakup
  • Underway: July - August 2025
    • Herder Drive rehabilitation from Hewlett Park trail to south of Harrison Road
    • Harrison Road rehabilitation from Herder Drive to Hallgren Drive
    • July 8 update: Starting to remove asphalt and construction to follow shortly afterwards
  • Complete: May - June 2025
    • Herder Drive from Hagerman Road to the Hewlett Park trail
    • Concrete repairs and final layer of asphalt