The Northeast Gateway Water Supply Main project is designed to improve water quality in Sylvan Lake. This is part of a long-term water sustainability project for the community, as directed by the 2020 Water Master Plan(External link). It will enhance system reliability and how treated water gets to Lakers. All the work being performed has been and continues to be discussed and shared with the province, County of Red Deer, and CN Rail to ensure we continue to meet their requirements. This work includes:
Installing a second water supply main that ties to the North Reservoir
Assessing the old water main to plan for future enhancements
Why?
Reducing our dependency on the existing water supply main
Increasing water supply capacity to the lower zone
Enhancing the north water supply main will ensure long-term sustainability for future cost savings
Increasing the life cycle of the north water supply system
Where?
The project begins at the North Reservoir and follows Township Road 391 to Range Road 12 (30 Street), ending at Cuendet Industrial Way
Stage 1 - September 2025 to December 2025: Contract Tendering & Financial Approval (Complete)
Stage 2 - Estimated February 2026 to December 2026: Construction
Stage 3 - Estimated Fall 2026 to Fall 2027: Remediation
How does this impact residents, and what do you need to know?
Water service will remain active throughout the project
Access to residents and businesses will be maintained at all times
Traffic will be reduced to one lane while passing active construction sites
Detour routes will be implemented at times when full road closures are required
The new supply main will extend the life of the system and prepare the community for long term needs
No changes to water quality are anticipated, and all work is conducted under strict regulatory and operational controls
The hours of construction shall be from 7:00 AM to 7:00 PM Monday to Saturday. Sunday work and evening work may also be required as weather and schedule requirements dictate.
Read more about the Water Master Plan(External link) and stay tuned for more information on how the Town is investing in a healthy water future for Lakers.
The Northeast Gateway Water Supply Main project is designed to improve water quality in Sylvan Lake. This is part of a long-term water sustainability project for the community, as directed by the 2020 Water Master Plan(External link). It will enhance system reliability and how treated water gets to Lakers. All the work being performed has been and continues to be discussed and shared with the province, County of Red Deer, and CN Rail to ensure we continue to meet their requirements. This work includes:
Installing a second water supply main that ties to the North Reservoir
Assessing the old water main to plan for future enhancements
Why?
Reducing our dependency on the existing water supply main
Increasing water supply capacity to the lower zone
Enhancing the north water supply main will ensure long-term sustainability for future cost savings
Increasing the life cycle of the north water supply system
Where?
The project begins at the North Reservoir and follows Township Road 391 to Range Road 12 (30 Street), ending at Cuendet Industrial Way
Stage 1 - September 2025 to December 2025: Contract Tendering & Financial Approval (Complete)
Stage 2 - Estimated February 2026 to December 2026: Construction
Stage 3 - Estimated Fall 2026 to Fall 2027: Remediation
How does this impact residents, and what do you need to know?
Water service will remain active throughout the project
Access to residents and businesses will be maintained at all times
Traffic will be reduced to one lane while passing active construction sites
Detour routes will be implemented at times when full road closures are required
The new supply main will extend the life of the system and prepare the community for long term needs
No changes to water quality are anticipated, and all work is conducted under strict regulatory and operational controls
The hours of construction shall be from 7:00 AM to 7:00 PM Monday to Saturday. Sunday work and evening work may also be required as weather and schedule requirements dictate.
Read more about the Water Master Plan(External link) and stay tuned for more information on how the Town is investing in a healthy water future for Lakers.
Share Stage 2: Pre-construction Set to Begin on FacebookShare Stage 2: Pre-construction Set to Begin on TwitterShare Stage 2: Pre-construction Set to Begin on LinkedinEmail Stage 2: Pre-construction Set to Begin link
Pre-constructionof theNortheast Gateway Water Main Project will begin on February 23, 2026. This project is designed to improve water quality in Sylvan Lake.
It will enhance systemreliability and how treated water gets to Lakers.
During construction:
Water service will remain active
Your water remains safe to use
Access to residents and businesses will be maintained at all times
Traffic will be reduced to one lane while passing active construction sites
Detour routes will be implemented at times when full road closures are required