This project builds up to five new groundwater supply wells. The new wells will providedrinking water. We anticipatelocating the new wells in Red Deer County, near the Summer Village of Jarvis Bay.
Why
Sylvan Lake is growing
We need more water within 5 years to meet demand
The new wells will supply the north reservoir
Load balancing: Spread load across more wells to protect our aquifer from overdraft and subsidence (page 14, page 24)
How
Survey any residents (within 1.6 Km of the new well locations) about existing groundwater supply wells.
Because the new well locations are near Jarvis Bay and Red Deer County residents, we are making sure there are no negative impacts
Gather information to choose new well locations
Well drilling and testing
Apply for a Provincial Water Act License
Construction: Design and build the new wells. Connect them to the Town’s north reservoir
Who
We found that the Jarvis Bay and Red Deer County has privately owned and operated wells
We asked nearby residents to help us identify existing wells through a survey
The survey results help us understand the local groundwater system
Contractor
We hired ISL Engineering and Land Services (ISL) to:
Help us identify new well locations
Assistandsupervise well drilling, installation, and connectionto the Town water system
This project builds up to five new groundwater supply wells. The new wells will providedrinking water. We anticipatelocating the new wells in Red Deer County, near the Summer Village of Jarvis Bay.
Why
Sylvan Lake is growing
We need more water within 5 years to meet demand
The new wells will supply the north reservoir
Load balancing: Spread load across more wells to protect our aquifer from overdraft and subsidence (page 14, page 24)
How
Survey any residents (within 1.6 Km of the new well locations) about existing groundwater supply wells.
Because the new well locations are near Jarvis Bay and Red Deer County residents, we are making sure there are no negative impacts
Gather information to choose new well locations
Well drilling and testing
Apply for a Provincial Water Act License
Construction: Design and build the new wells. Connect them to the Town’s north reservoir
Who
We found that the Jarvis Bay and Red Deer County has privately owned and operated wells
We asked nearby residents to help us identify existing wells through a survey
The survey results help us understand the local groundwater system
Contractor
We hired ISL Engineering and Land Services (ISL) to:
Help us identify new well locations
Assistandsupervise well drilling, installation, and connectionto the Town water system
Share 2023/2024 Survey Results on FacebookShare 2023/2024 Survey Results on TwitterShare 2023/2024 Survey Results on LinkedinEmail 2023/2024 Survey Results link
On the Town’s behalf, the Summer Villages of Sylvan Lake administration sent survey forms to property owners within the Summer Villages of Jarvis Bay (210 surveys in 2023) and Birchcliff (192 surveys in 2024). A small number of surveys were also hand delivered to Kayton Estates and elsewhere in Red Deer and Lacombe Counties.
Results
125 people responded
120 people indicated they had a water well on their property
112 people told us their well was for household use
75% with a well provided shared some well information with us
70% of the wells are used constantly or regularly during the day, 18% are used a few days a week or a few days a month. One well was not in use anymore. The rest did not provide information.
Some residents reported only using their well seasonally, usually in summer
We had three reports of the water having a slight odor, one report of high iron content and one report of high incidences of fluoride
There were multiple reports of the water being good quality and soft
Questions?
If you have any questions about surveys or the water wells project, please ask them here
Share Budget on FacebookShare Budget on TwitterShare Budget on LinkedinEmail Budget link
This project is still in the design phase. Design phases provide concrete details so that we can then create more accurate cost estimates.
Total Budget: Estimated $3,000,000
Funding Source: 30%, or $900,000 is covered by a grant form the Province of Alberta. The remainder is covered by reserves
Phase 1
Budget: $2,970,000
Funding Source: Reserves and grants
Progress: Underway
Page last updated: 25 Mar 2025, 09:15 AM
Have Your Say
Groundwater well verification survey
New Water Wells has finished this stage
We are inviting Jarvis Bay and Red Deer County residents who live close to new well areas to complete the survey. The survey closes on June 30, 2023.
Survey Results
New Water Wells is currently at this stage
The survey closed on June 30 for evaluation and review of results. The project team will report back on key outcomes.
Final report
this is an upcoming stage for New Water Wells
We are documenting the final outcomes of the consultation survey here. This may include a summary of all contributions collected as well as recommendations for future action.