Project Phases
May 01 → November 15 2023
Phase 1 COMPLETE: Survey and Find Well Locations
Phase 1
May - June: Groundwater well verification survey
Gather information to choose new well locations
- Fall 2023: Well drilling and testing
- November 28, 2023: Darcy’s Drilling Services of Ponoka was awarded the drilling contract for an estimated five production wells and five observation wells in Red Deer County
- More field investigations are needed in the late winter/early spring. Future phases are delayed because the wells drilled so far are below our expectations
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
January 01 2024 → July 07 2025
UNDERWAY: Phase 2 (Drilling and Testing)
Well drilling
Testing:
Quality of water
Production volume
June 02 → September 30 2025
UNDERWAY: Phase 3 (Drilling and Licensing)
Phase 3
- Drilling 6 new wells
- January 22, 2024 - July 2025 (Underway)
- Drilling is weather dependent
- This project includes one existing well near the north reservoir. We are bringing that well online. It will also need a license
- 2025: Apply for Provincial Water Act Licenses for the 6 new and one existing well
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
May 01 2025 → December 31 2026
ESTIMATED: Phase 4 (Completion of construction)
Phase 4
- Finish construction
- Connection of the new wells to the Town’s north reservoir for treatment and distribution
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time