Centennial Street Redevelopment 2025

Share Centennial Street Redevelopment 2025 on Facebook Share Centennial Street Redevelopment 2025 on Twitter Share Centennial Street Redevelopment 2025 on Linkedin Email Centennial Street Redevelopment 2025 link

This project is complete for 2025. 

Next Phase: Centennial Street (from 50 Avenue to Lakeshore Drive)

  • Fall 2025 engagement: Have your say about the design of the next phase. Construction for this phase starts in 2027, after the 2026 construction break
  • 2026: Break from construction 
  • 2027: Construction resumes




The 50 Street Redevelopment Project upgrades 50 Street from Lakeshore Drive to 48 Avenue. Upgrades include new infrastructure (road surface)underground infrastructure (utilities), sidewalks, and landscaping. All downtown businesses in the 50 Avenue Redevelopment construction area are open. CN Rail completed the railway crossing upgrades. The project has three phases running from 2023 to 2027. There is a planned two year break for 2025 and 2026

When: Phases

  • Phase 1 and 2, COMPLETE: 2013 - 2024
  • Phase 2 part 2: 2025. Builds on previous work
  • Planned break: 2026 - 2026. Regardless of start time, there is a planned two year break between Phase 2 and 3
  • Phase 3: Tentatively starting in 2027

The 50 Street Redevelopment Project upgrades 50 Street from Lakeshore Drive to 48 Avenue. Upgrades include new infrastructure (road surface)underground infrastructure (utilities), sidewalks, and landscaping. All downtown businesses in the 50 Avenue Redevelopment construction area are open. CN Rail completed the railway crossing upgrades. The project has three phases running from 2023 to 2027. There is a planned two year break for 2025 and 2026

When: Phases

  • Phase 1 and 2, COMPLETE: 2013 - 2024
  • Phase 2 part 2: 2025. Builds on previous work
  • Planned break: 2026 - 2026. Regardless of start time, there is a planned two year break between Phase 2 and 3
  • Phase 3: Tentatively starting in 2027

This project is complete for 2025. 

Next Phase: Centennial Street (from 50 Avenue to Lakeshore Drive)

  • Fall 2025 engagement: Have your say about the design of the next phase. Construction for this phase starts in 2027, after the 2026 construction break
  • 2026: Break from construction 
  • 2027: Construction resumes




Questions about the Centennial Street Modernization project Phase 2?

  • We are listening
  • If you have questions about the Centennial Street construction ask them here
  • We are doing our best to answer as quickly as we can