March 01 → November 19 2027

ESTIMATED: Phase 3, Construction

We hope to start this phase at this time, but it still is an estimated start date. We'll let you know once we confirm start dates!

Tasks 

  • Construction of Centennial Street: 50 Avenue to Lakeshore Drive 
  • Limiting July and August construction wherever possible  
  • Improve accessibility such as widening sidewalks and wheelchair ramps, rolled curbs, and more
  • Installing new underground infrastructure such as new stormwater drainage and soil cells that work together with trees to improve the downtown stormwater system
    • Improve safety by routing stormwater from downspouts underground and into soil cells, instead of through grated trenches or onto the sidewalk
    • This reduces the amount of ice in the winter, making shopping downtown during the winter more inviting and accessible 
  • We'll post more details about this phase as they become available


Why can't we do construction projects according to a set schedule?

  • Weather is the boss of construction. If we have bad weather, we have to delay projects
  • Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
  • Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
  • There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time

 We thank you for all your patience during construction to keep our workers safe!

July 01 2025 → December 31 2026

ESTIMATED: Planned break from construction

To allow for businesses to have a break from continual construction, we are hoping to pause for two years. 

This two year pause applies to the Centennial Street project.

September 2024 → June 2025

UNDERWAY: Phase 2 Intersection Construction

We hope to start this phase at this time, but it still is an estimated start date. We'll let you know once we confirm start dates!

Tasks 

Part 1, 2024: Reconstruction of the intersection at 50 Avenue and Centennial Street

  • Remove old asphalt, concrete curbs, and sidewalks 
  • Install underground wiring conduit for the new traffic signals 
  • Excavate and install a new gravel structure to provide a base for a new asphalt road surface 
  • Install new curbs and gutters 
  • Install new sidewalks 
  • Pave the road with asphalt 
  • Install a new asphalt walking path on the east side of the intersection 
  • Landscaping 
  • CN Rail and Fortis are also working on upgrades 

Part 2, 2024: 

  • Install traffic lights

Part 3, 2025

  • Minor, short-term construction
  • Final layer of asphalt
  • Line painting
  • Any remaining landscaping
  • Because we halt construction for the summer, some phase 2 tasks must be completed in 2025 

Why can't we do construction projects according to a set schedule?

  • Weather is the boss of construction. If we have bad weather, we have to delay projects
  • Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
  • Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
  • There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time

 We thank you for all your patience during construction to keep our workers safe!

January → August 2024

COMPLETE: Phase 1, Approvals, design, construction

Completed tasks 

  • Approval from CN Rail and Transport Canada before scheduling construction dates 
  • May 27 - Jul 1: Construction along 50 Avenue from 49 Street to Centennial Street. Although this work is on 50 Avenue, this must be completed before we can work on the Centennial Street and 50 Avenue intersection and rail crossing. Major construction paused for the summer
  • Limited July and August construction wherever possible
  • July 15: Concrete pile bases for the new traffic lights at Centennial Street and 50 Avenue. To maintain traffic flow, we are constructing one pile at a time. The intersection will remain fully open during construction
  • Completed before Canada Day: 
    • Concrete sidewalks and building property accesses from 50 Avenue
  • Completed before 1913 Days:
    • June 10: Pouring concrete curbs and gutters  
    • June 13: Adding a layer of asphalt to the 50 Avenue and Centennial Street intersection
  • February 14, 2024: Posted the Request For Proposal to find a construction contractor for phase 1 
  • Review submissions from the Request for Proposal and choose a construction contractor 
  • Chose contractor for phase 1, awarded to Border Paving (See page 86 of March 25 Council Agenda
  • April - May 2024: New upgraded underground stormwater mains at the 50 Avenue and Centennial Street intersection


January 2014 → November 2023

COMPLETE: Pre-Planning and Design

Completed tasks 2014 - 2022

  • The Town has been preparing and planning for this project since 2014

  • 2014 and 2015 saw public engagement sessions on the future of the waterfront and 50 Street

  • Many other projects had to be completed before we started the Centennial Street project, including reports, design concepts, and other construction projects

  • Reports completed:

  • Designs completed :

    • West Village overall detail design
    • 50 Avenue, west of Centennial Street to 60 Street
    • Sylvan Lake Regional Wastewater Commission (SLRWWC) south shore sanitary trunk line
    • West Annexed Lands (West of 60 Street from Lakeshore Drive to Hwy 11) sanitary trunk
    • Transportation Canada and CN Rail design approvals
  • Construction completed:

    • Lakeshore Drive Modernization
    • Cobb’s block water and sanitary main replacement
    • 50a Avenue watermain replacement, Centennial Street  to 52 Street 
    • West Village sanitary main replacement and relining
    • 50a Street modernization
    • 50a Avenue modernization
    • 53 Street Rehabilitation
    • 50 Avenue rehabilitation, 33 Street to 50 Street
    • Hampton Pointe stormwater lift station
    • New upgraded underground water and sewer mains at the 50 Avenue and Centennial Street intersection


Completed tasks - 2023

  • Resident priorities
  • Conceptual designs
  • Preliminary design
  • Detailed design. Because of the rail crossing, intersection design is constrained by Transportation Canada and CN Rail


Benefits

  • Water: stronger water mains that are less likely to burst or leak

  • Storm: Improved water drainage and reduced risk of localized flooding

  • Road: Improved accessibility and safety, and

  • Overall: Area more visually pleasing