April 27, 2023 Progress Report

From April 17 - April 26, we:

  1. Completed water valve cut ins
  2. Installed temporary water services

On April 27, our first road closure started and we started work on:

  1. Road excavation
  2. Installing new water, sewer and storm main lines

Learn more

Questions?

Share April 27, 2023 Progress Report on Facebook Share April 27, 2023 Progress Report on Twitter Share April 27, 2023 Progress Report on Linkedin Email April 27, 2023 Progress Report link

Construction is now complete on the redevelopment of 50 Avenue, from Lakeshore Drive to Centennial Street.

2028: We estimate that the next phase of 50 Avenue redevelopment, from Centennial Street to 60 Street, will begin around 2028.