South Reservoir Enhancements

Share South Reservoir Enhancements on Facebook Share South Reservoir Enhancements on Twitter Share South Reservoir Enhancements on Linkedin Email South Reservoir Enhancements link

The South Reservoir Project is designed to improve water quality in Sylvan Lake. This is part of a long-term water sustainability project for the community, as directed by the 2020 Water Master Plan. It will enhance system reliability and how treated water gets to Lakers. This work includes:

  • Installing baffle curtains to increase contact time repairing internal and external valves and reconfiguring the South reservoir discharge path
  • Improve water treatment by increasing contact time and reducing short circuiting inside
  • The well pump and pipe system will be decommissioned
  • Replacing and removing pumps and valves that have reached the end

The South Reservoir Project is designed to improve water quality in Sylvan Lake. This is part of a long-term water sustainability project for the community, as directed by the 2020 Water Master Plan. It will enhance system reliability and how treated water gets to Lakers. This work includes:

  • Installing baffle curtains to increase contact time repairing internal and external valves and reconfiguring the South reservoir discharge path
  • Improve water treatment by increasing contact time and reducing short circuiting inside
  • The well pump and pipe system will be decommissioned
  • Replacing and removing pumps and valves that have reached the end of their life cycle

Why?

  • To streamline operation and reduce long term maintenance costs
  • Extend the life cycle of the south system
  • Enhancing the south system will ensure long-term stainability for future cost savings
  • To reduce energy usage and increase response times

When?

Multiple phases, including:

  • December 8 & 9, 2025: Upgrades and equipment installation
  • Winter 2025/26 to Spring 2026: Mechanical work in Beacon Hill, minor tie-ins, initial reservoir preparations, and upgrades to monitoring equipment
  • Summer to Fall 2026: Structural modifications, electrical upgrades, new piping installations, and continued reservoir improvements
  • Fall 2026 to Winter 2027: Final baffle installations, recirculation upgrades, pump decommissioning, reservoir cell draining and cleaning, and long-term operational switchover

How does this impact residents, and what do you need to know?

  • Water will not be wasted. It will be sent to the community as it was intended to be
  • Water service will remain active throughout the project
  • Construction impacts will be coordinated to minimize service disruptions
  • Occasional short overnight pressure reductions may occur for mechanical tie-ins
  • Residents may notice brief pressure fluctuations, but no extended service interruptions are expected
  • No changes to water quality are anticipated, and all work is conducted under strict regulatory and operational controls
  • Construction activity will occur on-site at the reservoir and pump stations, with minimal impact to surrounding areas
  • This project improves water quality and simplifies long term operations expected
  • The upgrades will extend the life of the system and prepare the community for long term needs

Read more about the Water Master Plan and stay tuned for more information on how the Town is investing a healthy water future for Lakers.

Ask questions about the South Reservoir project

Questions about the South Reservoir project?

  • We are listening
  • If you have questions about the South Reservoir project ask them below
  • We are doing our best to answer as quickly as we can