Project Phases
April 01 2022 → November 30 2024
ESTIMATED: Water monitoring
Work planned for 2022 - 2024 includes:
- Semi-annual groundwater and surface water monitoring
- Desludging cell 7 (dredging and recycling)
August 01 → December 31 2023
COMPLETE: Monitoring
Work completed in 2023 :
- Semi-annual ground water and surface water monitoring
April 01 → November 30 2022
COMPLETE: Monitoring contract awarded, plans, and surveys
Work completed in 2022 includes:
- Three year (2022-24) annual groundwater and surface monitoring program awarded to WSPE & I CanadaLimited (consultants)
- Sludge survey for Cells 7 and 8
- Financial plan updated
April 01 → November 30 2021
COMPLETE: Planning and design
Work completed in 2021:
- Phase III Environmental Site Assessment and preliminary design of proposed snow dump (Cell 7)
- Land use/feasibility assessment options for storage cells
- Groundwater monitoring
April 01 → November 30 2020
COMPLETE: Planning and studies
Work completed in 2020 includes:
- The 10-year plan for reclamation was approved by Alberta Environment and Parks.The plan still must be approved by Alberta Environment and Protected Areas (AEPA).
- Groundwater monitoring
- Phase II Environmental Site Assessment
- Snow disposal site feasibility study