Project Phases
April 01 2026 → November 12 2031
ESTIMATED: Future Phases
2026 - Area 2 (Yellow)
- Budget: $7,000,000
- Synthetic Turf Field
- Parking Lots 2 & 3
- Soccer Fields x 2 (grass)
2028 - Area 3 (Orange)
- Budget: $4,000,000 Unfunded (Funds are not secured yet)
- Amenities Building
- Outdoor Rink
- Outdoor Leisure Ice
- Trail Development
2030 - Area 4 (Pink)
- Budget: $3,200,000 Unfunded (Funds are not secured yet)
- Pickle Ball Courts
- Tennis Courts
- Operations Yard
- Trails & Landscaping
2031 - Area 5 (Purple)
- Budget: $1,300,000 Unfunded (Funds are not secured yet)
- Trails & Landscaping
- Parking Lot OR Little League Diamond
June 01 → August 31 2024
ESTIMATED: Opening campground and tournament house
We are planning to open the campground and tournament house in summer 2024.
April 03 2023 → July 01 2024
Phase 3
Work planned for 2023 includes:
Detailed design
Installation of remaining water, sanitary and storm lines
Construction of RV campground
Construction of Tournament House
Roads, parking lots and trails for campground and quad baseball facility
Site landscaping and irrigation system
Shallow utilities to service campground and tournament house
February 01 2021 → December 14 2022
COMPLETE: Phase 2
Tasks completed 2021 - 2022 include:
- Detailed design
- Play zone: spray park, playground, trails, and sidewalks
- Washroom facility
- Site landscaping
- Main road and designated parking areas paving
- Underground utilities (water, sanitary, storm and shallow utilities)