Phase 4 Construction and Baseball Diamond Improvements Set to Begin
Phase 4 Construction is scheduled to start in May 2026 and be completed in December 2026. This work includes:
Synthetic Turf Field
- 4 Pickleball Courts
Roads B & C (see project map)
Parking Lot 3
Irrigation
Operations Yard
Budget:
Budget: $7,400,000
How does this impact park users, and what do you need to know?
There should be no interruptions to park spaces or services.
Traffic may be reduced to one lane while passing active construction sites. For news on lane closures check view our news hub here
Baseball diamond Improvements are scheduled to start in May 2026.
Why?
During wet weather, the baseball diamonds have been affected by water pooling.
What work will be done?
Remove existing shale
Re-grade the clay base layer
Ensure the sub-drainage system is working
Place new drainage rock and shale
When?
The first ball diamond will be closed for construction from May 2026 to the start of June 2026
The final three ball diamonds will be closed for construction from September 8, 2026, to October 2026
How does this impact ball diamond users, and what do you need to know?
Construction will happen before and after peak season
We are not closing all ball diamonds at once. Ball diamonds not under construction will be available to rent and use throughout construction
Budget:
Budget: $387,000