December 2023 Update
Pogadl Park phase 3 construction is underway, with a new end date of July 2024 for phase 3. We hope to open the campground and tournament house in the summer of 2024.
Completed Tasks:
- Detailed design
- Electrical primary
- Installation of water, storm, and sanitary lines
- RV campground loop paving
In progress:
- RV campground construction
- RV pad paving
- Landscaping
- Tournament house construction
- Roads, parking lot, and trails
- Landscaping and irrigation
- Electrical secondary
Share December 2023 Update on Facebook
Share December 2023 Update on Twitter
Share December 2023 Update on Linkedin
Email December 2023 Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends