December 2023 Update

Pogadl Park phase 3 construction is underway, with a new end date of July 2024 for phase 3. We hope to open the campground and tournament house in the summer of 2024.
Completed Tasks:
- Detailed design
- Electrical primary
- Installation of water, storm, and sanitary lines
- RV campground loop paving
In progress:
- RV campground construction
- RV pad paving
- Landscaping
- Tournament house construction
- Roads, parking lot, and trails
- Landscaping and irrigation
- Electrical secondary