Budget
The Heritage Management Plan is split over 3 phases. The progress of the plan is determined by how much funding we get for each phase.
Phase 3: Final Plan & Adoption
- Budget: TBD
-
Funding Source:
- Future Application: 50% Government of Alberta Heritage Preservation Partnership Program (grant)
- Pending Council Approval: 50% Municipal Operating Budget (tax dollars)(External link)
- Progress: 2026. Scheduled, based on grant funding award
Phase 2: Draft Plan Development
- Budget: TBD
-
Funding Source:
- Application underway: 50% Government of Alberta Heritage Preservation Partnership Program (grant)
- Council approved: 50% Municipal Operating Budget (tax dollars)(External link)
- Progress: Fall 2025. Scheduled, based on grant funding award
Phase 1: Background Research
- Budget:$50,000
-
Funding Source:
- Secured: 50% Government of Alberta Heritage Preservation Partnership Program (grant)
- Secured: 50% Municipal Operating Budget
- Progress: Underway. Spring 2025
Questions?
Share Budget on Facebook
Share Budget on Twitter
Share Budget on Linkedin
Email Budget link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends