June 24, 2026 Update:

Construction is underway for Herder Drive from Harrison Road to Herder Drive Trail (north of Heenan Crescent):

June 15 – July 10, 2026

  • Concrete repairs
    • Curbs
    • Sidewalks
  • Laying final layer of asphalt
  • Line painting
  • Landscaping

Construction is underway for Herder Drive from 47 Avenue to Harrison road:

June 22 - July 22:

  • Replacing concrete curbs and sidewalks
  • Removal of existing asphalt
  • Roadway work
    • Reshaping of gravel base
    • There’ll be intermitted roadway closures and traffic disruptions during construction. At all times, we’ll ensure that people will have pedestrian access to their property. There’ll be times when parking along Herder Dr will not be allowed, and vehicular access to properties will not be allowed. We’ll be informing people in advance of any traffic disruptions. Find traffic interruptions and road closure announcements on the News Hub.
    • Residents impacted by this work will receive advance notice

July 20 - July 31

  • First and second final layer of asphalt
  • There’ll be intermitted roadway closures and traffic disruptions during construction. At all times, we’ll ensure that people will have pedestrian access to their property. There’ll be times when parking along Herder Dr will not be allowed, and vehicular access to properties will not be allowed. We’ll be informing people in advance of any traffic disruptions. Find traffic interruptions and road closure announcements on the News Hub.
  • Residents impacted by this work will receive advance notice

August 3 - August 8

  • Landscaping
  • Line Painting

Why can't we do construction projects according to a set schedule?

  • Weather is the boss of construction. If we have bad weather, we must delay projects
  • Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
  • Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
  • There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time

We thank you for all your patience during construction to keep our workers safe!