Phases

Phase 2 Part 3, 2025

Completed

  • Remaining landscaping
  • Signage
  • We are working on fine tuning the traffic lights to work together to reduce congestion, including the traffic lights at:
    • Centennial Street and 50 Avenue
    • Lakeshore Drive and Centennial Street, including changing the intersection to a scramble style crossing. Details here
    • 48 Avenue and Centennial Street
  • We are working to halt any construction for the busy summer months
  • We hope to wrap up construction this year for the 2026 construction break, resuming in 2027

We thank you for all your patience during construction to keep our workers safe!


Phase 2 part 2

Completed

  • Concrete, first level of asphalt, line painting, and signage
  • Fortis installed the streetlights along 50 Avenue
  • CN Rail intersection upgrades including preparation of the pedestrian crossing at the railway along the east side of 50 Street
  • Remove old asphalt, concrete curbs, and sidewalks
  • Install underground wiring conduit for the new traffic signals
  • Excavate and install a new gravel structure to provide a base for a new asphalt road surface
  • Install new curbs and gutters
  • Install new sidewalks
  • Pave the road with asphalt
  • Reconstruction of the intersection at 50 Avenue and Centennial Street
    • Install a new asphalt walking path on the east side of the intersection
    • Landscaping
    • CN Rail and Fortis are also working on upgrades
    • Install traffic lights. Scheduled for the end of November. We turn them on in the spring of 2025. First, CN must remove, replace, and upgrade their equipment so the traffic signals can coordinate with the rail crossing signals
    • Traffic lights turn on

    • Final layer of asphalt with line painting

    • Line painting
    • Paving of trail along south side of 50 Ave and east side of 50 St


Share Phases on Facebook Share Phases on Twitter Share Phases on Linkedin Email Phases link

This project is complete for 2025. 

Next Phase: Centennial Street (from 50 Avenue to Lakeshore Drive)

  • Fall 2025 engagement: Have your say about the design of the next phase. Construction for this phase starts in 2027, after the 2026 construction break
  • 2026: Break from construction 
  • 2027: Construction resumes