Snow is here! October 24, 2023 Update

Progress on the 50 Avenue and 46 Street intersection is slightly delayed due to this week's snowfall. The project is on budget. All downtown businesses in the 50 Avenue Redevelopment construction area are open.

What's new

  • Snowfall this week slightly delayed construction progress
  • Construction has resumed
  • Starting October 30:
    • Landscaping
    • 50 Avenue from 49 Street to 50 Street: install underground water and wastewater lines

Next Tasks

  • Work being finished October 16 - 31:
    • Concrete work
    • The first layer of asphalt paving (west of 46 Street)
  • Work being finished October 23 - November 6:
    • Underground utilities (trunk mains for water and wastewater)
Completed
  • Started October 9 - 13: Fortis started streetlight installation
Detours to expect for October 24 - November 6.
Detours changes as work progresses.


Streamlining Construction Schedules for 2024

  • 50 Avenue is now open from 50 Street to 46 Street
  • 50 Avenue is remaining open over the winter, until construction resumes in spring 2024
  • Construction on the library parking lot is underway. This parking lot is above much underground infrastructure (water, sewer), and completing this work in 2023 helps us to shorten construction schedules in 2024. This shortens how much construction must be done during the buy summer season
  • This work includes relocating the water and sewer lines from underneath 50 Avenue, to underneath the parking lot (49 Street to 50 Street). If we need repairs in the future, 50 Avenue won't be disrupted along this important economic corridor
  • Doing the work in the fall of 2023 instead of spring/summer 2024:
    • Minimizes impacts on the businesses in the area
    • Reduces how much work we need to do in 2024, which makes 2024 construction faster
    • Gives underground work and earth time to settle over the winter of 2023 / 2024. This means that any problems from settling, like dips or cracks, can be corrected in spring 2024. This should create a smoother surface in the future
    • Surface work (paving, concrete, line painting, street lights, etc.) can start earlier in 2024, which means we can finish paving in 2024 instead of 2025
    • Keeps us on schedule with the new wastewater trunk main line. The new line is part of a separate project we are doing together with the Sylvan Lake Regional Wastewater Commission (SLRWWC). The new line can't go forward until the 50 Avenue work is done


Access to businesses during construction

  • All downtown businesses in the 50 Avenue Redevelopment construction area are open

  • Varsity Mall: all accesses open, please watch for construction traffic

  • Dairy Queen: all accesses open, please watch for construction traffic

  • Railway Plaza: all accesses open, please watch for construction traffic

  • Monarchos Centre: all accesses open, please watch for construction traffic

  • Library: The parking lot partially reopens on October 30, access from 50 Avenue

  • Party Chef: Access from 50 Avenue and 49 Street (Concrete sidewalk beside Party Chef was completed Monday October 16)

Learn more

Questions?

Share Snow is here! October 24, 2023 Update on Facebook Share Snow is here! October 24, 2023 Update on Twitter Share Snow is here! October 24, 2023 Update on Linkedin Email Snow is here! October 24, 2023 Update link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>