November 10, 2023 Update

Progress on the 50 Avenue and 46 Street intersection is on budget. All downtown businesses in the 50 Avenue Redevelopment construction area are open.

What's new

  • November 10: Replacing services (water/sewer) to buildings on 50 Avenue from 49 Street to 50 Street

Next Tasks

  • Underway: Landscaping
  • Underway: 50 Street and 50 Avenue closures: continue the water/sewer main lines upgrades. See closures below:
Estimated November 2 - 24
Finished
  • Removed temporary above ground water lines east of 49 Street
  • 50 Avenue from 46 Street to 49 Street is paved with the first layer of asphalt. We are adding the final layers of asphalt in 2024
  • The library parking lot now has a gravel surface and is open

Streamlining Construction Schedules for 2024

  • 50 Avenue is now open from 50 Street to 46 Street
  • 50 Avenue is remaining open over the winter, until construction resumes in spring 2024
  • Construction on the library parking lot is complete. The lot will remain gravel until paving in 2024. This parking lot is above much underground infrastructure (water, sewer), and completing this work in 2023 helps us to shorten construction schedules in 2024. This shortens how much construction must be done during the buy summer season
  • This work includes relocating the water and sewer lines from underneath 50 Avenue, to underneath the parking lot (49 Street to 50 Street). If we need repairs in the future, 50 Avenue won't be disrupted along this important economic corridor
  • Doing the work in the fall of 2023 instead of spring/summer 2024:
    • Minimizes impacts on the businesses in the area
    • Reduces how much work we need to do in 2024, which makes 2024 construction faster
    • Gives underground work and earth time to settle over the winter of 2023 / 2024. This means that any problems from settling, like dips or cracks, can be corrected in spring 2024. This should create a smoother surface in the future
    • Surface work (paving, concrete, line painting, street lights, etc.) can start earlier in 2024, which means we can finish paving in 2024 instead of 2025
    • Keeps us on schedule with the new wastewater trunk main line. The new line is part of a separate project we are doing together with the Sylvan Lake Regional Wastewater Commission (SLRWWC). The new line can't go forward until the 50 Avenue work is done


Access to businesses during construction

  • All downtown businesses in the 50 Avenue Redevelopment construction area are open

  • Varsity Mall: all accesses open, please watch for construction traffic

  • Dairy Queen: all accesses open, please watch for construction traffic

  • Railway Plaza: all accesses open, please watch for construction traffic

  • Monarchos Centre: all accesses open, please watch for construction traffic

  • Library: Access from 50 Avenue. All accesses open including the library parking lot

  • Party Chef: Access from 50 Avenue and 49 Street

Learn more

Questions?

Share November 10, 2023 Update on Facebook Share November 10, 2023 Update on Twitter Share November 10, 2023 Update on Linkedin Email November 10, 2023 Update link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>