Project Phases
UNDERWAY: Phase 3, Stage 6 (45 Street to 49 Street)
Phase 3, Stage 6
- 50 Avenue, from 45 Street to 49 Street
Tasks
Landscaping
No road closures are needed for this work
Concrete work: miscellaneous curb work, flower beds
June 21: pouring the concrete pad in front of the Library
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
COMPLETE: Phase 4, Stage 2a (49 Street to 50 Street)
Phase 4 2a
- 50 Avenue, from 49 Street to 50 Street
Tasks
Work on wastewater lines
No sidewalk or road closures are needed for this work
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
COMPLETE: Phase 4, Stage 1 (49 Street to the laneway west of 50 Street)
We hope to start the first stage of this phase at this time, but it still is an estimated start date.
We'll let you know once we confirm start dates!
Phase 4
- 50 Avenue, from 49 Street to the laneway west of 50 Street (beside Sylvan Auto Center)
Tasks
Replacement of aging underground infrastructure, water mains, sanitary mains, storm mains, and lot services
Adding a stormwater main and catch basins to fix drainage issues and improve stormwater flow
Utilities
Replacing all shallow utilities such as power, gas, and cable, if needed
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
COMPLETE: Phase 3, Stage 5 (46 Street to 49 Street)
We hope to start the first stage at this time, but it still is an estimated start date.
We'll let you know once we confirm start dates!
Phase 3, Stage 5
- 50 Avenue, from 46 Street to 49 Street
Tasks
Roadway Modernization
Improving pedestrian walkability and safety with the addition of wide side walks, cross walks and curb bulb-outs
Replacing curb and gutter and adding more catch basins to improve drainage
Adding improved street lighting along
Installing the first layer of asphalt
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
COMPLETE: Phase 3, Stage 4 (Panago to 49 Street)
We hope to start the first stage at this time, but it still is an estimated start date.
We'll let you know once we confirm start dates!
Phase 3, Stage 4
- 50 Avenue, from Panago to 49 Street
Tasks
Underground Infrastructure (COMPLETE)
Replacement of aging underground infrastructure, water mains, sanitary mains, storm mains, and lot services
Adding a stormwater main and catch basins to fix drainage issues and improve stormwater flow
Roadway Modernization (UNDERWAY)
Improving pedestrian walkability and safety with the addition of wide side walks, cross walks and curb bulb-outs
Replacing curb and gutter and adding more catch basins to improve drainage
Adding improved street lighting along
Utilities
Replacing all shallow utilities such as power, gas, and cable, if needed
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
COMPLETE: Preparation for 50 Avenue & 50 Street
As part of the 50 Ave redevelopment, we are planning on making improvements to the intersection at 50 Avenue and 50 Street. This intersection is often congested. It's difficult to cross east to west, and it's hard for drivers to see pedestrians.
We are improving:
- Pedestrian and traffic safety
- Underground services such as replacing aging sewer and water mains
Traffic interruptions:
- Once CN Rail gives the go ahead, we are doing exploratory work in the intersection
- Please expect full closures for north to south traffic, and partial closures for east to west
Why we must explore:
- Before we can improve the intersection, we have to explore what is underground
- The infrastructure at the intersection could be 40 - 50 years old, and sometimes older. Record keeping from that time often doesn't capture all the details needed for planning improvements
- Once we know what we are looking at, we'll know the most cost-effective way to improve infrastructure both below ground and above ground
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
COMPLETE: Phase 3, Stage 3 (Dairy Queen to Panago)
Phase 3, Stage 3
- 50 Avenue, from Dairy Queen to Panago
Tasks
Underground Infrastructure (COMPLETE)
Replacement of aging underground infrastructure, water mains, sanitary mains, storm mains, and lot services
Adding a stormwater main and catch basins to fix drainage issues and improve stormwater flow
Roadway Modernization (COMPLETE)
Improving pedestrian walkability and safety with the addition of wide sidewalks, cross walks and curb bulb-outs
Replacing curb and gutter and adding more catch basins to improve drainage
Adding improved street lighting along
Utilities
Replacing all shallow utilities such as power, gas, and cable, if needed
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
COMPLETE: Phase 3, Stage 2 (45 Street to just past 46 Street)
We hope to start the first stage at this time, but it still is an estimated start date.
We'll let you know once we confirm start dates!
Phase 3, Stage 2
- 50 Avenue, from 45 Street to just past 46 Street (Estimated May 1 - June 15)
Tasks
Underground Infrastructure
Replacement of aging underground infrastructure, water mains, sanitary mains, storm mains, and lot services
Adding a stormwater main and catch basins to fix drainage issues and improve stormwater flow
Roadway Modernization
Improving pedestrian walkability and safety with the addition of wide side walks, cross walks and curb bulb-outs
Replacing curb and gutter and adding more catch basins to improve drainage
Adding improved street lighting along
Utilities
Replacing all shallow utilities such as power, gas, and cable, if needed
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
COMPLETE: Phase 3 - Stage 1 (50 Avenue Junctions)
Phase 3, Stage 1
- Valve cut-ins on 46 Street, 47 Street, and 48/49 Street junctions along 50 Avenue
- Includes Intersection improvements at 50 Avenue and 46 Street
Tasks
Underground Infrastructure
Replacement of aging underground infrastructure, water mains, sanitary mains, storm mains, and lot services
Adding a storm water main and catch basins to fix drainage issues and improve storm water flow
Roadway Modernization and Traffic Calming
Improving pedestrian walkability and safety with the addition of wide sidewalks, crosswalks, and curb bulb-outs
Replacing curb and gutter and adding more catch basins to improve drainage
Adding improved street lighting along
Intersection improvements at 50 Avenue and 46 Street.
Utilities
Replacing all shallow utilities such as power, gas, and cable, if needed
Why can't we do construction projects according to a set schedule?
- Weather is the boss of construction. If we have bad weather, we have to delay projects
- Construction supplies sometimes arrive on time, sometimes they arrive late. For example, if concrete supplies for sidewalks are delivered late, we can't start the construction
- Sometimes we find surprises in the ground. We make every effort to survey before breaking ground, but sometimes we find underground utilities like gas lines that are in unexpected places. This forces us to create a new plan, which can cause a time delay
- There are more surprises that can happen too! We plan things down to the last detail, but plans are never 100% perfect, 100% of the time
We thank you for all your patience during construction to keep our workers safe!
COMPLETE: Phase 2, 50 Avenue from 38 Street to 45 Street
Tasks
Full removal and replacement of all concrete and road structure,
Addition of storm water mains and catch basins,
Replacement of water main from 40 street to 45 street,
Replacement of underground house services,
Addition of a 2.5m sidewalk,
Addition of traffic calming measures, and
Burial of overhead powerlines and house electrical services.
Benefits
Water: stronger water mains that are less likely to bursting and leaking,
Storm: Improved water drainage and reduced risk of localized flooding,
Road: Improved pedestrian safety, and
Overall: Area more visually pleasing.
COMPLETE: Phase 1, 50 Avenue from 33 Street to 38 Street
Tasks
Full removal and replacement of all concrete and road structure
Addition of storm water mains and catch basins
Replacement of water main from33 Street to 38 Street
Replacement of underground house services
Addition of a 2.5m sidewalk
Addition of traffic calming measures
Burial of overhead powerlines and residential electrical utilities
Install a new storm water lift station at Erickson Drive to improve drainage and reduce flooding downtown and in Hewlett Park and Hampton Pointe
Benefits
Water: stronger water mains that are less likely to bursting and leaking
Storm: Improved water drainage and reduced risk of localized flooding
Road: Improved pedestrian safety, and
Overall: Area more visually pleasing