April 18, 2024 Update
Construction on the roundabout is beginning soon. When phase 1 begins, the intersection will become a right in right out only. This change along with detours is tentatively scheduled for May 6. Please plan for alternate routes. Thanks in advance for your patience and kindness with the construction workers and other drivers navigating the changes.
Phase 1: Dates TBD
- Starting April 22: Hydro vacuum work on underground crossings
-
Expected early May:
- Memorial Trail may require full closure for up to 2 days at certain times
- Fortis line move
- No left turns:
- From Highway 20 northbound lane onto westbound Memorial Trail
- From Highway 20 southbound lane onto eastbound Township Road 384
- From Memorial Trail eastbound lane onto northbound Highway 20
- From Township Road 384 westbound lane onto southbound Highway 20
Phase 2: Dates TBD, expected start mid June, 2024
-
No left turns:
- From Highway 20 northbound lane onto westbound Memorial Trail
- From Highway 20 southbound lane onto eastbound Township Road 384
- From Memorial Trail eastbound lane onto northbound Highway 20
- Township Road 384 CLOSED at Highway 20
- Memorial Trail may require full closure for up to 2 days at certain times
Ask & Answered
- Ask questions about this project
Open House
- Consider yourself invited to ask questions and check out the new design drawings
- Pop into the Government of Alberta's Highway 20 Functional Planning Study open house at the same time
- April 25, 2024
- NexSourceCentre, 4823 49 Ave, Sylvan Lake
- 5:00 PM - 8:00 PM
- Can't make it? View the open house boards and ask questions here
Share April 18, 2024 Update on Facebook
Share April 18, 2024 Update on Twitter
Share April 18, 2024 Update on Linkedin
Email April 18, 2024 Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends