Budget
The 50 Avenue redevelopment is one of the Town's biggest projects. It could not be completed in one construction season and was split into 3 phases. Phases 1 and 2 are complete.
Total budget to date: $16,254,000
Phase 4
- Budget: TBD
- Funding Source: TBD
- Progress: Starting spring 2024
Phase 3
- Budget: $5,228,000
- Funding Source: Reserves and grants
- Progress: Starting spring 2023
Phase 2
- Budget: $6,116,000
- Funding Source: Reserves and grants
- Progress: Complete
Phase 1
- Budget: $4,910,000
- Funding Source: Reserves and grants
- Progress: Complete
Questions?
Share Budget on Facebook
Share Budget on Twitter
Share Budget on Linkedin
Email Budget link
Construction is now complete on the redevelopment of 50 Avenue, from Lakeshore Drive to Centennial Street.
2028: We estimate that the next phase of 50 Avenue redevelopment, from Centennial Street to 60 Street, will begin around 2028.