The 50 Avenue redevelopment is one of the Town's biggest projects. It could not be completed in one construction season and was split into 3 phases. Phases 1 and 2 are complete.

Total budget to date: $16,254,000

Phase 4

  • Budget: TBD
  • Funding Source: TBD
  • Progress: Starting spring 2024

Phase 3

  • Budget: $5,228,000
  • Funding Source: Reserves and grants
  • Progress: Starting spring 2023

Phase 2

  • Budget: $6,116,000
  • Funding Source: Reserves and grants
  • Progress: Complete

Phase 1

  • Budget: $4,910,000
  • Funding Source: Reserves and grants
  • Progress: Complete

Questions?

Share Budget on Facebook Share Budget on Twitter Share Budget on Linkedin Email Budget link

Construction is now complete on the redevelopment of 50 Avenue, from Lakeshore Drive to Centennial Street.

2028: We estimate that the next phase of 50 Avenue redevelopment, from Centennial Street to 60 Street, will begin around 2028.